Road Subsidence Remediation with Shear Lock Piles on Messenger Road
Subsidence has occurred at three locations on the eastern side of the Messenger Road carriageway between RP270m and RP465m. The subsidence has resulted in the formation of longitudinal cracking within the eastern side of the road including the crest of the roadside shoulder. The remediation works will comprise the inst…
Source ID: NZ-GETS-25371175
Estimated value
As published by the source; may be updated by the buyer.
Scope overview
Subsidence has occurred at three locations on the eastern side of the Messenger Road carriageway between RP270m and RP465m. The subsidence has resulted in the formation of longitudinal cracking within the eastern side of the road including the crest of the roadside shoulder.
The remediation works will comprise the installation of staggered shear lock piles within the roadside shoulder to provide lateral support and mitigate the potential for on-going subsidence.
Buyer & contacts
Tags & Signals
Similar tenders
Timber Pole Retaining Wall Remediation and Reconstruction Project
A 30-meter timber pole retaining wall is showing significant signs of failure with exposed concrete encasements causing outward rotation. Remediation involves constructing an in-ground palisade wall behind the existing structure while replacing damaged footpath, kerb, and channel. The affected carriageway pavement will be fully reinstated as part of the comprehensive repair works.
Timber Pole Retaining Wall Construction and Road Safety Improvements
This project involves constructing a timber pole retaining wall along a 25-meter section with a retained height of up to 2 meters. Additional work includes pavement rehabilitation and installation of a compliant semi-rigid crash barrier with end terminals. The improvements aim to enhance road safety and infrastructure stability in the specified area.
Brigham Creek Road Subsidence Remediation Works Tender Invitation
This tender invites Physical Works Panel members to bid on remediation works for subsidence on Brigham Creek Road. The project involves constructing a timber pole retaining wall to support the carriageway where an existing keystone wall has failed. The works will also include treating and reinstating the affected pavement area.
Unlock the full IndexBox Tenders workspace
Get hourly updates across 100k+ opportunities, AI recommendations, and one-click autopilot workflows. Zero obligation.
Disclaimer: IndexBox Tenders does not issue, announce, or publish this tender. This information is aggregated from publicly available sources and is provided for informational purposes only. IndexBox Tenders is not affiliated with, endorsed by, or acting on behalf of the tender issuer. Users should verify all information directly with the official tender source before making any decisions or taking any action.