Retaining Walls and Maintenance Pad Construction at Kopuawhakapata Stream Culvert
This contract is for the construction of retaining walls and a concrete maintenance pad at the Kopuawhakapata Stream Culvert that runs beneath Hirini Street in Kaiti, Gisborne. The Gisborne District Council has identified the following objectives for the contract: � Construction of new sheetpile retaining wall to act a…
Source ID: NZ-GETS-22182684
Estimated value
As published by the source; may be updated by the buyer.
Scope overview
This contract is for the construction of retaining walls and a concrete maintenance pad at the Kopuawhakapata Stream Culvert that runs beneath Hirini Street in Kaiti, Gisborne.
The Gisborne District Council has identified the following objectives for the contract: � Construction of new sheetpile retaining wall to act as wingwalls beside existing culvert; � Construction of new precast concrete headwall on top of existing culvert; � Construction of a new concrete maintenance pad to make maintenance/clearing of culvert inlet easier for maintenance staff; � Protection of the existing culvert, wingwalls, headwall and surrounding services throughout construction; � Tie-in with surrounding area and the works already completed as part of the Rakaiatane Road upgrades and improve amenity of the area.
No work may be carried out within the stream bed after 1 May 2020. Absolutely no extension will be granted for works in the stream bed after this date.
Buyer & contacts
Tags & Signals
Similar tenders
Dunedin City Council Seeks Contractor for Retaining Wall Repairs
The Dunedin City Council is seeking an experienced contractor to repair two failing retaining walls at Brown Street and Sidey Street. The project requires expertise in retaining wall construction, working at heights, and ground anchor installation to address safety concerns. The contractor must demonstrate proactive communication and cost management, with completion required by May 31, 2025.
Construction of New 36-Bunk Hut at Pouakai Hut Site in Egmont National Park
This project involves constructing a new 36-bunk hut at the existing Pouakai Hut site on the Mangorei Track within Egmont National Park. The scope includes demolition of the current 16-bunk hut, building new facilities including four toilets and a wastewater management system, and completing site works with retaining walls and vegetation removal. Following construction, the site will be remediated to restore the natural environment.
Dunedin Road Reserve Slip Repairs Requiring Retaining Wall Construction
The Dunedin City Council seeks a contractor to repair four slips in road reserves caused by July 2022 rain events. The work involves constructing retaining walls using soil nail and gabion basket techniques while managing communication with affected residents. All repairs must be completed by April 30, 2024, to minimize disruption.
Keep reading for free. Pay only when you need workspace actions.
This record stays public. Upgrade only when you want alerts, exports, OCR packs, and autopilot workflows inside the private workspace.
Disclaimer: IndexBox Tenders does not issue, announce, or publish this tender. This information is aggregated from publicly available sources and is provided for informational purposes only. IndexBox Tenders is not affiliated with, endorsed by, or acting on behalf of the tender issuer. Users should verify all information directly with the official tender source before making any decisions or taking any action.