Watermain and Footpath Infrastructure Project in Hanmer Springs
The project is located in Hanmer Springs, North Canterbury. The proposed watermain runs from Argelins Road intersection through to 148 Hanmer Springs Road, SH7A. The proposed footpath runs from Argelins Road intersection through to 168 Hanmer Springs Road, SH7A to meet existing concrete footpath. The contract will oper…
Source ID: NZ-GETS-25120672
Scope overview
The project is located in Hanmer Springs, North Canterbury. The proposed watermain runs from Argelins Road intersection through to 148 Hanmer Springs Road, SH7A. The proposed footpath runs from Argelins Road intersection through to 168 Hanmer Springs Road, SH7A to meet existing concrete footpath. The contract will operate as separable portions for the two projects, both being delivered concurrently.
The proposed watermain works consist of installation of approximately 350 metres of DN180 PE 100 PN12.5 and DN63 PE80 PN12.5 rider-main which will be in a common trench with the DN180. The project will also consist of valves, fire hydrants, gate valves, and the connection of all laterals in conjunction with the new mains.
The existing watermain and laterals will be required to remain �live� during construction to maintain services to local residential properties and shall be abandoned with the connection of the new mains to the existing network. The proposed footpath works consist of ground preparation, installation rehabilitation of approximately 45 metres of lime chip footpath and 470 metres of concrete footpath.
This will include wooden batten and concrete edging, respectively, including driveway crossings. The Contractor is to supply and install all valves, fittings and to perform all pipe welding. Hurunui District Council will supply the DN180 PE100 PN12.5, but they shall liaise with the pipe supplier for the timing of the pipe deliveries.
The Contractor will also be responsible for all health, safety and environmental aspects of the project. The Contractor will be responsible for the reinstatement of all surfaces.
Buyer & contacts
Tags & Signals
Similar tenders
Watermain Installation Project Between Grassmere Street and Mays Road
This contract involves the installation of a new OD355 PE trunk watermain connecting Grassmere Street and Mays Road. The project focuses on upgrading water infrastructure to improve service reliability in the area. The work includes pipeline installation and associated construction activities.
Watermain Pipeline Construction Project in Hanmer Springs
This project involves constructing a new watermain pipeline along Chalet Crescent in Hanmer Springs, North Canterbury. Stage 1 includes approximately 600 meters of DN180 and 580 meters of DN63 watermain installation, road crossings, and associated valve and hydrant fittings. Stage 2 is a separable portion that may continue the pipeline loop depending on available budget.
Watermain Installation and Commissioning Tender for Florence Place Infrastructure
This tender seeks contractors for the supply, installation, and commissioning of OD125 mm and OD63 mm watermains along Florence Place, including associated valves, fittings, and connections. Submissions must be made electronically through the Government Electronic Tenders Service (GETS) by 3pm on Wednesday, 10 March 2021. Only pre-qualified tenderers in Class 1 Water Works Simple B will be considered for this project.
Keep reading for free. Pay only when you need workspace actions.
This record stays public. Upgrade only when you want alerts, exports, OCR packs, and autopilot workflows inside the private workspace.
Disclaimer: IndexBox Tenders does not issue, announce, or publish this tender. This information is aggregated from publicly available sources and is provided for informational purposes only. IndexBox Tenders is not affiliated with, endorsed by, or acting on behalf of the tender issuer. Users should verify all information directly with the official tender source before making any decisions or taking any action.